Water supply wells for Welwitschia Breweries

Client Name
ABInBev Namibia
Location
Otjozondjupa Region, Namibia

Challenge

Namibia is the driest Sub-Sahara country due to its unique climate influenced by the Benguela current. Not surprisingly, water resource is scarce and heavily dependent, not only on rainfall amount, but also on rainfall patterns, particularly in the Central Areas where dams are the primary source of water supply.

Since the supplying dam levels lowered to a dramatic 12% at the end of 2016, ABInBev (then SABMiller) engaged with SLR to locate borehole sites for additional sustainable water supply for their operation plant situated in Okahandja (80km north of Windhoek, Namibia’s capital city), much needed to develop further their supply.

Solution

ABInBev’s operations require a daily volume of water of 360m3. SLR has planned and managed the successful drilling of four boreholes thus far and additional ones are underway. The project targeted fractures and faults in the complex impermeable rock structures where water flows.

Impact

ABInBev is now able to safely draw 720m³ during peak production periods from these new sources of water.


Related projects

See all projects
  • Project

    Fort William, UK

    Alvance British Aluminium

    Manufacturing & Industry

    Environmental Impact Assessment - Alvance


    Read more
  • Project

    Various Waste Management Companies

    Infrastructure

    Landfill Leachate Methane Stripping Plants (MSP)


    Read more
  • Project

    Otjozondjupa Region, Namibia

    ABInBev Namibia

    Manufacturing & Industry

    Water supply wells for Welwitschia Breweries


    Read more